NPTEL Project Management Week 7 Assignment Answers 2024

Sanket
By Sanket

NPTEL Project Management Week 7 Assignment Answers 2024

1. What is the actual cost of the project right now?

  • $1800
  • $2000
  • $2200
  • $2400
Answer :- For Answers Click Here 

2. Assuming that the COST variance experienced so far in the project will continue, how much more money will it take to complete the project?

  • $400
  • $440
  • $2800
  • $2840
Answer :- For Answers Click Here 

3. If the variance experienced so far were to stop, what is the project’s estimate at completion?

  • $2400
  • $2440
  • $2600
  • $2800
Answer :- For Answers Click Here 

4. What is the project’s TCPI using the project’s budget at completion?

  • 0.5
  • 1.0
  • 1.5
  • 2
Answer :- 

5. Senior management wants to the percentage of the project that is complete. What should you report?

  • 75%
  • 83%
  • 92%
  • 95%
Answer :- 

6. Imagine if instead of 10 months and costing $2200, the project was in month three and costing $4000. What formula might you use for BAC?

  • [(BAC – EV) / (CPI * SPI)] + AC
  • new bottom-up estimate
  • AC + new ETC
  • AC + BAC – EV
Answer :- For Answers Click Here 

7. Probabilistic scheduling is useful

  • when the duration of project tasks is uncertain.
  • in “really new” projects.
  • in projects involving tasks that are outside the control of the project team.
  • All of these
Answer :- 

8. Revisions to a project schedule are necessary when

  • Critical resources are unavailable
  • he original plan is no longer feasible or desirable
  • Deadlines have been changed
  • All of the above
Answer :- 

9. The first step in project crashing is:

  • Choose the task or tasks on the critical path with the lowest crash cost
  • List the crash costs for each task in the project
  • Update the lengths of all affected paths in the network
  • Identify new critical paths
Answer :- 

10. The crash cost data are estimates of the additional costs of:

  • Adding workers
  • Using overtime pay
  • Reducing tasks by one-time unit
  • All of the above
Answer :- For Answers Click Here 
Share This Article
Leave a comment