NPTEL Project Management For Managers Week 5 Assignment Answers 2023
1. Which of the following is not a measure of risk?
- Range
- Standard deviation
- Coefficient of variation
- Mean
Answer :- For Answer Click Here
2. PRAM Stands for?
- Project Risk Aversion and Management
- Project Analysis and Management
- Project Risk Analysis and Management
- Project Risk Allocation and Management
Answer :-
3. John Strauss is a Project Manager for a reforestation project. To identify the risks involved, John sends a questionnaire to gather inputs from experts. Which technique is John using?
- Delphi technique
- Interviews
- Brain storming
- Documentation review
Answer :- For Answer Click Here
4. Which of the following is correct sequence for phases of risk assessment?
- Define, Identify, Focus, Estimate
- Define, Estimate, Evaluate, Focus
- Define, Focus, Identify, Structure
- Define, Identify, Focus, Manage
Answer :-
5. Which of the following is not a source of a risk?
- Financial risk
- Project specific risk
- Competitive risk
- Market risk
Answer :-
6. Accounting Break Even Analysis is equal to __.
- A.B.E = (Fixed cost – Depreciation)/Contribution margin ratio
- A.B.E = (Depreciation – Fixed cost)/Contribution margin ratio
- A.B.E = (Contribution margin ration + Fixed cost)/Depreciation
- A.B.E = (Fixed costs + Depreciation)/Contribution margin ratio
Answer :-
7. Which of the following is not a technique for stand-alone risk analysis?
- Sensitivity analysis
- Market analysis
- Scenario analysis
- Simulation analysis
Answer :-
8. What is the correct sequence of steps in Simulation analysis?
- Model the project, Select a value, Specify the value, Determine the value of NPV
- Model the project, Select a value, Determine the value of NPV, Specify the value
- Model the project, Determine the value of NPV, Select a value, Specify the value
- Model the project, Specify the value, Select a value, Determine the value of NPV
Answer :-
9. Project Risk = _____________* Consequences of Event.
- Loss
- Outcomes of Event
- Probability of Event
- None of the above
Answer :- For Answer Click Here
10. Calculate standard deviation for the given data:
NPV Probability
200 0.3
600 0.5
900 0.2
- 240.3
- 249.8
- 232.5
- 267.9
Answer :-