NPTEL Project Management for Managers Week 8 Assignment Answers 2024

Sanket
By Sanket

NPTEL Project Management for Managers Week 8 Assignment Answers 2024

1. What is the difference between CPM and PERT

  • CPM is deterministic while PERT is probabilistic
  • Both are deterministic
  • Both are probabilistic
  • CPM is probabilistic, PERT is deterministic
Answer :- For Answers Click Here 

2. Which of the following is not correct in PERT?

  • The time duration is probabilistic
  • There is an expected duration of the project
  • Simulation can be used to PERT network
  • All are deterministic in nature.
Answer :- For Answers Click Here 

3. When are dummies added?

  • Creating multiple sources
  • Creating multiple sinks
  • Creating multiple sources and sink
  • Creating a single source or single sink
Answer :- For Answers Click Here 

4. What is the difference between PERT and CPM?

  • PERT is event-oriented, and CPM is activity-oriented.
  • PERT is activity-oriented, and CPM is event-oriented.
  • Both are event-oriented.
  • Both are activity-oriented.
Answer :- 

5. What is the critical path?

  • It is the longest path of the whole network.
  • It is the shortest path of the whole network.
  • It is the average path in the whole network.
  • It is the longest time taking a path in the whole network.
Answer :- 

6. What are independent floats?

  • It is the time that an activity can be delayed without delaying the project.
  • It is the amount by which its duration can be increased without affecting project time or subsequent activity.
  • Duration by which an activity could be extended.
  • Independent float is the shortest time.
Answer :- For Answers Click Here 

7. What is t_o and t_p with respect to PERT?

  • Optimistic time and most likely time.
  • Most likely time and pessimistic time.
  • Optimistic time and pessimistic time.
  • Pessimistic time and optimistic time.
Answer :- 

8. What is the variance in the network?

  • [(to−tp)/12]
  • [(tp−to)/12]2
  • [(tp−to)/6]2
  • [(tm−to)/6]2.5
Answer :- 

9. Which one of the following is assumed for timing the activities in PERT network?

  • Alpha-distribution
  • Beta-distribution
  • Binomial distribution
  • Erlangen distribution
Answer :- 

10. Critical path is good for

  • The small project only
  • The large project only
  • Both small and large projects only
  • Neither small nor large projects
Answer :- For Answers Click Here 