NPTEL Project Management for Managers Week 8 Assignment Answers 2024
1. What is the difference between CPM and PERT
- CPM is deterministic while PERT is probabilistic
- Both are deterministic
- Both are probabilistic
- CPM is probabilistic, PERT is deterministic
Answer :- For Answers Click Here
2. Which of the following is not correct in PERT?
- The time duration is probabilistic
- There is an expected duration of the project
- Simulation can be used to PERT network
- All are deterministic in nature.
Answer :- For Answers Click Here
3. When are dummies added?
- Creating multiple sources
- Creating multiple sinks
- Creating multiple sources and sink
- Creating a single source or single sink
Answer :- For Answers Click Here
4. What is the difference between PERT and CPM?
- PERT is event-oriented, and CPM is activity-oriented.
- PERT is activity-oriented, and CPM is event-oriented.
- Both are event-oriented.
- Both are activity-oriented.
Answer :-
5. What is the critical path?
- It is the longest path of the whole network.
- It is the shortest path of the whole network.
- It is the average path in the whole network.
- It is the longest time taking a path in the whole network.
Answer :-
6. What are independent floats?
- It is the time that an activity can be delayed without delaying the project.
- It is the amount by which its duration can be increased without affecting project time or subsequent activity.
- Duration by which an activity could be extended.
- Independent float is the shortest time.
Answer :- For Answers Click Here
7. What is t_o and t_p with respect to PERT?
- Optimistic time and most likely time.
- Most likely time and pessimistic time.
- Optimistic time and pessimistic time.
- Pessimistic time and optimistic time.
Answer :-
8. What is the variance in the network?
- [(to−tp)/12]
- [(tp−to)/12]2
- [(tp−to)/6]2
- [(tm−to)/6]2.5
Answer :-
9. Which one of the following is assumed for timing the activities in PERT network?
- Alpha-distribution
- Beta-distribution
- Binomial distribution
- Erlangen distribution
Answer :-
10. Critical path is good for
- The small project only
- The large project only
- Both small and large projects only
- Neither small nor large projects
Answer :- For Answers Click Here